Greenscape Capital Group Inc.: Construction at Denver Green Park LLC Site Substantially Ahead of Schedule
Greenscape Capital Group Inc. ("Greenscape") is pleased to provide the following corporate update on construction at Denver Green Park LLC's 4,200 stall green parking facility serving the Denver International Airport in Denver, Colorado.
Construction is significantly ahead of schedule and is on budget. The facility is targeted to open in November 2010.
Steel erection on Building A is scheduled to complete on September 3rd, 2010. Delivery of steel for Building B (the larger of the two buildings) will take place on August 30th, 2010 with roof and wall sheets arriving approximately one week later. The steel erector will start on Building B on August 30th, 2010 which is approximately 3 weeks ahead of schedule. It is now estimated that the steel erection will complete on Building B on October 5th, 2010.
Greenscape is completely current and compliant with all material obligations and commitments relating to the rapidly advancing development. To date, Greenscape has injected approximately $6 million in capital to the construction process. As previously announced, Denver Green Park LLC has also closed a US $8.5 million loan with Wells Fargo Bank, having a 3 year term and an all-in fixed interest of 5.45% per annum until maturity.
Bryan Slusarchuk, Greenscape CEO, states, "It is wonderful to see the Denver project advancing so rapidly. Being substantially ahead of schedule and on budget is reflective of the hard work and professionalism of the crew onsite in Denver. Greenscape recently announced that Denver will serve as a model for future green parking developments with our partners at Propark so we are especially pleased to see the construction process at Denver exceeding expectations."
Steel erection on Building A is scheduled to complete on September 3rd, 2010. Delivery of steel for Building B (the larger of the two buildings) will take place on August 30th, 2010 with roof and wall sheets arriving approximately one week later. The steel erector will start on Building B on August 30th, 2010 which is approximately 3 weeks ahead of schedule. It is now estimated that the steel erection will complete on Building B on October 5th, 2010.
Greenscape is completely current and compliant with all material obligations and commitments relating to the rapidly advancing development. To date, Greenscape has injected approximately $6 million in capital to the construction process. As previously announced, Denver Green Park LLC has also closed a US $8.5 million loan with Wells Fargo Bank, having a 3 year term and an all-in fixed interest of 5.45% per annum until maturity.
Bryan Slusarchuk, Greenscape CEO, states, "It is wonderful to see the Denver project advancing so rapidly. Being substantially ahead of schedule and on budget is reflective of the hard work and professionalism of the crew onsite in Denver. Greenscape recently announced that Denver will serve as a model for future green parking developments with our partners at Propark so we are especially pleased to see the construction process at Denver exceeding expectations."